The Building of the M1

John Clark, January 2020

John was already known to us as a member but what we did not know that for 30 years he had worked for John Laing the construction company that is responsible for so many projects, not the least of which was the building of the M1. He brought with him a unique 30 minute flm that had been donated to ‘The National Film and TV Archive’ by the company for public use and interest.

The origins of the company stemmed from John Laing, a family owned building firm from Carlisle. In 1926 they moved to London. They prospered and acquired many contracts, growing 1600 fold between the two world wars.  Despite their entrepreneurial success they did not neglect their employees. Stemming from a strict Brethren Church background they displayed integrity and honesty. Workers had paid holidays, hours were reduced and pensions introduced which all contributed to strong company loyalty.

In 1958 John Laing won the contract to build Britain’s first long distance motorway. Laing’s were responsible for the 55 mile section, covering five counties. This  started in Slip End and finished at Crick in Northamptonshire. Using the largest machinery in the UK work started in the summer of 1958. Despite appalling weather conditions with a wet summer followed by a cold winter the project was finished to time in October 1959 at a cost of £16 million.

The route was divided into 4 sections each with their own office depots. To accommodate these and the main headquarters at Newport Pagnall 350 acres of land was rented. Detailed surveys were made of the route and problems of access ironed out. Engineers calculated the exact amount of earth to be moved – over 11million cubic metres in total. At least 200 complex structures had to be designed including 132 bridges. A wide variety of heavy machinery was used for the different tasks involved.

The workforce were recruited from far and wide. For every mile 70 men were needed. Many of them were housed in temporary accommodation.

While the rail bridges were made of steel, the road bridges were made of preformed concrete. Carpenters constructed the forms which were filled with concrete. These were then slotted into place to make the bridges which are still in use today.

All this happened long before the days of the mobile phone. On a project of this size quick communication was vital. To this end Laings set up their own short wave radio system and used a helipcopter to survey progress.

Laings always tried to organise their constructions with the minimum of disruption and damage. It is to their credit that rail services were never interrupted and the only road to be blown up was Clyde Road in Dunstable.

We were fortunate to have several family Laing employees join us for the evening and an impressive collection of  memorabilia to pore over during the interval. For my part I find it hard to equate the photos of earth moving machines deep in mud with the finished product.